That’s just one of the problems that the water project
faced. Here’s a bullet list through the head of some of the irregularities:
• Likely
substitution of inferior materials for materials listed in the specifications
on the part of the head engineer and the president and treasurer of the
citizens’ committee in charge of the project (this is soon to be verified or
refuted by an investigation to be carried out by the NGO that funded the
project)
• Likely theft of
the difference in cost of materials by the head engineer, president and
treasurer (ditto as regards the investigation)
• Collection of
fraudulent signatures on the part of the engineer’s assistant and use of those
signatures to validate documents stating that the engineer had provided
training to citizens in how to operate and maintain the well and its electric
pump
• Subsequent
flight of head engineer to the jungles of the Amazon (after first refusing to
answer his phone and finally changing his cell-phone number)
• The
aforementioned low voltage at the site of the well (located more than a
kilometer from the nearest transformer)
• Subsequent
petitions to ElectroNorte (the electric company) to install a new transformer
nearer the well and provide new posts and cable for the entire caserío of Rama
Guzmán at a cost of 150,000 soles ($55,000)
• Refusal on the
part of the president of the citizens’ committee in charge of the project to
donate the land on which the well is located after having publicly vowed to do
so in public meetings held prior to the inception of the project
• Unexplained
disappearance of all the materials left over after the “completion” of the
project
• Failure to in
fact complete the project; because there was no electricity the well produced
no water for over a year after its supposed completion
• Refusal on the
part of the president of the citizens’ committee to hand over the key to the well
hut so that the electric pump could be tested; refusal of the president to hand
over his copy of the specifications so that it could be determined if the
specified materials had or had not been purchased and installed
• Refusal of the
president and treasurer to attend any public meetings of the committee once
word got out about possible irregularities
If you’ve ever had a fishing reel backlash on you then you
can appreciate the complex nature of the untangling that each and every one of
the elements in this list required.
I won’t attempt to detail how we solved each of these
problems; instead let’s take one example, the electricity issue.
The problem was this: not only was the well too far from the
transformer but the “grid” in Rama Guzmán was hopelessly outdated and
overburdened, implemented twenty years ago for use by fewer than thirty
families and now being used by 80-100 families, many of which had simply
spliced into a neighbor or relative’s line and were sharing a meter. People had
extended the grid by erecting skinny wooden posts or tree trunks and stringing
low-tension wire from post to post in order to reach their houses. Where the
cable was adequate, trees had grown up and into the wiring, their limbs in
contact with the cable, drawing off current. As a result, instead of the
required 220 volts, the previously mentioned 110-140 volts were reaching the
well site.
ElectroNorte doesn’t hand out projects worth 150,000 soles
out of the goodness of its own heart. Many people and a few kindly coincidences
contributed to the eventual implementation of the project. Years ago Feliciano
Mendoza had rallied the population to petition a plan from ENSA. Each family
contributed 15 soles and ElectroNorte technicians came to Callanca, surveyed
and measured, determined the number of posts and the amount of cable required,
and drew up a plan illustrating the location of each electrical pole, the
transformer, etc. The problem was, there was no well project at that point and
so the plan didn’t include the well.
It would require a novel to recount all that we’ve been
through in the pursuit of 80 or so missing volts. First, in November, the JAS
(Junta de Agua y Saneamiento or Water and Sewage Committee) in Rama Guzmán
solicited a solution to the problem. ElectroNorte proposed a project that would
have included posts, cable and a meter so that they could charge Rama Guzmán
for the electricity consumed by the use of the pump. ElectroNorte’s solution
was that Rama Guzmán should pay the 2,500 soles that the project would’ve cost.
This would not have solved the problem, however; without a transformer (15,000
soles) nearer the well to generate the power to deliver 220 volts the pump
would not have operated or would have soon burned out due to the low voltage.
I’ll mention only briefly what happened during the following
months (bullet list number two):
• First a meeting
at ENSA with an enginner named César Manayay about the possibility of
implementing Felix Mendoza’s ambitious electrification project for all of Rama
Guzmán. He first said the project would be implemented in early 2012; later the
date slipped to “sometime in 2012.”
• A trip to
Chiclayo with the Alcaldesa of Mosefú, Rita Ayasta, and Victorio, the President
of Rama Guzmán’s JAS to speak with the General Manager of ElectroNorte and
request implementation of the aforementioned project or an immediate
provisional solution to the problem of low voltage at the well site.
• A follow-up
meeting with the General Manager in the office of the Alcaldesa in Monsefú. The
Gerente suggested a probable solution in “about a month-and-a-half.”
• Following these
meetings Engineer Manayay came to Rama Guzmán and made measurements for posts
and cable and asked us specific questions about the electric pump and the
energy requirements for the well. We asked how long it would take to schedule
the installation of the required components; “about a month-and-a-half,” he
said.
• A trip to
Ocinerg, the oversight agency for public utilities, to discuss the possibility
of filing a complaint against ENSA for poor-quality service (insufficeint
voltage) in Rama Guzmán. The Ocinerg lawyers encouraged us not to file a
complaint immediately but instead to try to work out an amiable solution with
ENSA.
• On Ocinerg’s
suggestion a trip to the ElectroNorte maintenance facility in Chiclayo. The
engineers there have direct control over resources and after consulting Engineer
Manayay they promised to look into the matter and give us an answer in a week.
• A week later I
called Maintenance. They said that they could not proceed without a formal
complaint filed with Ocinerg! If we filed a complaint how long would it take to
schedule the installation of the required components? “About a
month-and-a-half.”
• Since two weeks
of Engineer Manayay’s month-and-a-half had already passed I returned to him for
a solution. He said he thought I’d filed a complaint with Ocinerg. When I said
I hadn’t, not yet, he promised to coordinate with the General Manager of ENSA
and attempt to get the project back on track. I called three more times during the following weeks. The third
time Manayay told me that the problem had now been passed along to another
engineer, Enrique Llontop, who was responsible for projects in the Monsefú
area.
• I spoke with
Llontop; he and Manayay came to Rama Guzmán to investigate the situation. By
now I was speaking of the project with such familiarity and confidence that
Llontop mistook me for the engineer who had drilled the well and overseen the
water project. It turned out that Llontop’s family was from Callanca. Finally,
we’d encountered a friendly face at ElectroNorte.
Does this look to
you like a setup that would deliver 220 volts?
“About a month and a half” turned into about four months but
Llontop came through for us. He secured a transformer worth 15,000 soles from
his bosses at ElectroNorte. He put the project up for bids from outside vendors
whose work it would be actually to execute the project. That company arrived
and began to dig holes for posts and trim trees so that they wouldn’t interfere
with the new lines. From that point on only the normal number of screw-ups
occurred. For instance a dispute occurred because the road to the well is a
private right of way owned by two persons; the property line runs down the
middle of the road. When
ElectroNorte installed the posts leading to the well on one side of the road
the owner of that half of the road demanded that they be removed and installed
in the middle of the road so that they’d prejudice neither party. Everyone
managed to shine on in the face of such idiocies and the electric project was
finished by November of 2012, exactly one year after it was first proposed.
That’s how one and only one problem was resolved. If you
multiply the number of bullets in the second bullet list above by the number of
bullets in the first bullet list above you get the number of bullets we’ve
pumped into our brains over the course of the past year trying to solve all the
problems.
But none of that mattered so much on Saturday, January 12,
2013 when Miguel, a handyman from the Municipalidad, arrived at 7:00 o’clock in
the morning to drive the golden spike that would connect the two wayward
projects; that is, connect the well and its electric pump to the newly
completed electrical grid in Rama Guzmán. Was the connection a streamlined,
quick, efficient, high-tech procedure?
I’ll let you be the judge:
We’d scavenged about 50 meters of still-usable cable from
the 20-year-old cable that comprised the wiring replaced by that of the recently
completed electricity project. We carried a roll of this cable, a rickety
ladder made out of crooked tree limbs, a length of rope, a wire cutter, a
shovel and a machete with us to the well site. We used the ladder to access the
electric pole nearest the well. By tying the rope to the end of the heavy
electric cable and climbing high enough to attach the cable to the previously
erected wooden post and threading the length of rope (followed by the cable)
between tree limbs we were able to pass the cable from the first pole to the
second, attach the cable, and thread the rope between tree limbs to the next
post. In order to accomplish this one person stood on the ladder, another
climbed a tree and hauled the cable between mangos and through openings in the
foliage. When we got to the final post where the electric company´s cable ended,
we pulled the cable taut from below while Miguel affixed it to the post and
connected our cable to ENSA’s cable, standing not on the topmost rung of the
ladder but in fact on the tops of the two rails of the ladder in order to reach
the cable delivering the electric company’s 220 volts.
Digging up one of the electric poles from the obsolete project to use in an expansion of the new project.
At the well site, when we opened the door to inspect the
well itself, a few bats flew out of the well hut—a little brick casette housing
the well—that hadn’t been opened for a year. Everything seemed still to be in
place, nobody had stolen anything nor by the looks of things had there been any
serious deterioration of the components. Somebody climbed down into the well on
a metal ladder affixed to the concrete casing of the well. He called for us to
lower a rope; he tied something onto his end. We hauled up a 1.5 liter plastic
bottle half-filled with what had once been Inca Kola and that been floating in
the well water for a year.
A few meters from the well hut we dug a “pozo a tierra”
about a meter-and-a-half deep, a hole where we could drive a length of rebar
into the earth as a ground. We connected a length of copper wire to the rebar
and connected the ground to the the wiring that would eventually connect to the
control box for the pump. When the hole was dug and the ground installed, we
refilled the hole, shoveling in dirt, then pouring in buckets of water mixed
with mineral salts, then shoveling in more dirt.
We called Yesenia, a friend who was shopping in Chiclayo,
and asked her to buy us a thermo switch to act as a breaker for the system in
case of overloads or shorts. Miguel chiseled a few holes in the brick wall of
the well hut so that we could insert the ground wire and the wiring that
descended from the electrical pole nearest the well. He asked someone to bring
him a lightbulb from a house nearby so that he could verify that current was
reaching us. The lightbulb lit on the first try! He then chiseled a hole in the
concrete apron of the well hut so that we could bring the ground wire up to the
height of the switch, tested with the lightbulb again, and connected all the
wires to the switch inside the well hut, using a butter knife he’d borrowed from
a neighbor as a screwdriver.
We all watched anxiously while he tripped the switch, now
connected to the pump. The submersible pump hummed happily twenty feet below
us. Next we opened the lever that controlled the flow of water and my friend
Victorio climbed a metal ladder on the face of the well tower and looked into
one of the tanks. It was beginning to fill with water! It took the 1-horsepower
pump about 50 minutes to fill three 2,500-liter tanks.
Finally, we opened the valve that connected the tanks to the
community water system. Victorio ran to the nearest house and opened the valve
controlling the household’s water and connected a length of hose to the open
end of the pipe whose flow was controlled by the valve. I was watching from
about 50 meters away. I saw a jet of water shoot out of the end of the hose!
Everybody cheered.
I jumped on my bike and pedaled to the houses nearest the
well, then to a dirt lane that is the main thoroughfare of Rama Guzmán,
shouting, “Hay agua! Hay agua!” (Not “The British are Coming!” but “There’s
water!”) I stopped occasionally to watch a family test their connection and
confirm the arrival of the water and the force of the water pressure. Later in
the day we found and sealed a few leaks in the system but as of Sunday, the
following day, every family had its water.
It’s been said many times that water is life; that water is
the most basic element that sustains us; but let me say it one more time
because on this day it was clear exactly how much truth that statement contains.
And the element that sustains life is even sweeter when it’s been a little bit
difficult to come by.
One last thought: to the people I’m living with it’s a very,
very big deal, it’s a luxury and they’re delighted, when water comes out of a
hydrant in their front yard and they no longer have to haul it fifty meters in
buckets from the nearest hand-dug well. I don’t know if that thought
embarrasses you a little but it definitely does embarrass me. Not that that will keep me from whining about important stuff like too much foam in my latte when I get back to the U.S., but it's worth mentioning.
Yesenia (left) and Victorio (right).
Start working on that novel... (-;
ReplyDeleteI agree with Judith! Your persevering reminds me of all the out of the box thinking I used to do to get the job done behind the wheel of my plow truck in a rough a snow storm. Ha3!!! Seemed serendipitous that I read this post. I was @ the EPA in Boston this week taking part in coalition to develop a green workforce that does green infrastructure to reduce the stormwater problems we're facing. This insightful man talked about how in America our water problems are a prosperity problem. We've got so much that we don't value or take care of it. He told a story of how 150,000 people gathered in Boston to celebrate the day they opened the pipe the brought clean water to the City. To celebrate how the sicknesses would end. Hope we don't have to go backwards to wake up here in the States. Don't drink lattes much. Perhaps with you when you're back.
ReplyDelete